A newly formed planning body has overturned a council decision, which refused planning permission for a windfarm in the East Clare mountains.
A French Multinational has now cleared a major hurdle in its bid to deliver a 50-Mega Watt development at Lackareagh.
In a long-running saga that officially began 11 months ago, EDF Renewables lodged plans for a seven turbine windfarm, each up to 180m in height across the townlands of Kilbane, Killeagy, Shannaknock, Ballymoloney, Magherareagh and Lackareagh Beg.
The company claims the development would produce enough green energy to power 35,000 homes, while it’s also promised a community benefit fund worth €240,000 per year.
However, the plans met fierce local opposition, receiving more than 80 objections in just two months, most of which related to property devaluation, wildlife, mental health and traffic congestion.
Shannon Airport also weighed in, citing the potential adverse impacts on flight communication and navigation systems.
Clare County Council subsequently refused planning permission over biodiversity, visual, and pollution concerns.
This decision was quickly appealed and now the newly formed planning body An Coimisúin Pleanála has granted permission for the controversial project, which could operate for up to 35 years.
The commission has attached 26 conditions to the ruling, including that the turbines must be finished in a light grey colour.
Given the level of public opposition however, it’s likely the decision will be challenged by judicial review.